An accessory dwelling unit (ADU), whether a converted garage or a new backyard cottage, raises two electrical questions. Outside: how it is supplied, by a feeder from the house panel to a subpanel or by its own utility service, and whether the existing service can carry the added load. Inside: a small home with its own kitchen, bathroom and bedroom, wired to the same NEC dwelling rules as the main house. Both depend heavily on your jurisdiction.

Updated on Last checked NEC (NFPA 70) 2023

Key facts

  • 01How an ADU is supplied (feeder and subpanel from the main house, or a separate service and meter) depends on the jurisdiction and the utility, not on a single NEC rule.
  • 02A subpanel keeps neutral and ground separate (isolated neutral bar, 4-wire feeder): the neutral-to-ground bond exists only at the service (250.24(A)(5), 250.142(B)).
  • 03Adding an ADU to an existing service usually needs a load calculation for the added load (220.83 for existing dwellings, Article 120 in NEC 2026).
  • 04Inside, the usual dwelling rules apply: 2 × 20 A small-appliance circuits if there is a kitchen, a 20 A bathroom circuit, GFCI / AFCI, the 6 ft wall rule, smoke alarms.
  • 05A garage that becomes living space is wired as habitable rooms: receptacle spacing, AFCI, switched lighting, alarms.

ADU rules start at the permit office

The NEC does not have an "ADU article". What decides the electrical design is how the jurisdiction classifies the unit, what the utility allows for metering, and the general dwelling rules of the NEC and the IRC. Ask the permit office early: whether a separate meter is allowed or required, whether the ADU may be fed from the main house panel, and which load calculation they want to see.

Feeder from the house or separate service?

The two usual ways to power an ADU
OptionWhat it meansPoints to check
Feeder from the main panelA two-pole breaker in the house panel feeds a subpanel in the ADU through a 4-wire feeder (two hots, neutral, equipment ground)Room in the main panel; capacity of the existing service (load calculation); neutral and ground kept separate in the subpanel
Separate serviceThe utility installs a second meter (or the ADU gets its own service drop or lateral); the ADU panel is a service panelUtility rules and fees; whether the jurisdiction allows a second service on the lot; outdoor emergency disconnect (230.85) and surge protection (230.67) at that service
Which options are allowed, and which is cheaper, varies by jurisdiction and utility. This page does not cite ADU-specific code sections because they are local.

With a feeder and subpanel, the key grounding rule is that the neutral is bonded to ground only at the service disconnect of the main house (250.24(A)(5), 250.142(B)). In the ADU subpanel, the neutral bar is isolated from the enclosure and the equipment grounding conductors land on a separate ground bar. A detached cottage raises further grounding and feeder-routing questions that your electrician and inspector will settle locally.

Remember that the ADU subpanel or service panel is a panel like any other: 30 in wide, 36 in deep, 6.5 ft high working space (110.26), never in a bathroom or a clothes closet (240.24), and a complete circuit directory (408.4).

Can the existing service carry the ADU?

When the ADU is fed from the house, the permit office will usually want to see that the existing service can carry the added load. For an existing dwelling, the NEC has a dedicated method for added loads (220.83; relocated to Article 120 in NEC 2026). Like the optional method for one-family dwellings (220.82), it starts from 3 VA per ft² of floor area, 1,500 VA per small-appliance and laundry circuit and the nameplates of fastened-in-place appliances, applies demand percentages, then adds heating and cooling. Your electrician applies the exact percentages of the edition your jurisdiction uses.

What weighs most in an ADU: an electric range or cooktop, a water heater, a heat pump or mini-split, and a dryer if there is one. An all-electric ADU on a 100 A house service often brings the question of a service upgrade; a gas-heated main house on 200 A may have room. The calculation decides, not the rule of thumb. See residential load calculation (NEC 220).

Inside the ADU: the same dwelling rules as the main house

Typical studio or one-bedroom ADU (NEC 2023, IRC R314 / R315)
SpaceReceptacles and lightingCircuits and protection
Living / sleeping areaNo point along a wall more than 6 ft from a receptacle; wall-switched lighting outlet (or switched receptacle)AFCI; general 15 / 20 A circuits
Kitchen or kitchenetteCountertop receptacles: no point more than 24 in away; island provision for a future receptacle2 × 20 A small-appliance circuits; GFCI on all receptacles + AFCI
BathroomReceptacle within 3 ft of the basin; switched light; exhaust fan20 A bathroom circuit; GFCI
Laundry (if any)Receptacle for the washer20 A laundry circuit; GFCI + AFCI; 30 A 240 V dryer circuit
OutsideReceptacle at the entrance and switched entrance lightGFCI; weather-resistant receptacle with in-use cover
AlarmsSmoke alarm in the bedroom (or sleeping area), outside it and on each story; CO alarm with fuel-burning appliances or an attached garageHard-wired, battery backup, interconnected
Whether the ADU's alarms must be interconnected with the main house's is a local question.

Typical 240 V circuits in an ADU: a range at 40 A / 8 AWG (a two-burner cooktop or a compact range may be smaller, per its nameplate), a water heater at 30 A / 10 AWG for a 4,500 W element, and the heat pump or mini-split per its nameplate MCA and MOCP. Always size from the nameplates of the appliances actually chosen.

Garage conversion: what changes

  • A garage has its own NEC rules (a 20 A garage circuit, one receptacle per vehicle bay, GFCI). Once it becomes living space, the habitable-room rules apply instead: the 6 ft wall rule, AFCI, a wall-switched light in each room.
  • If the main panel is in the garage, it now sits in the ADU: keep its working space clear and make sure it does not end up in the new bathroom or a closet.
  • Draw the new rooms as they will be used (bedroom, kitchen, bathroom) and plan the circuits from that layout, rather than starting from the garage's existing receptacle circuit.

Backyard cottage: what changes

  • The feeder or the separate service has to reach the cottage: trench length, route and wire size are part of the design (voltage drop of 3 % on a branch and 5 % total is an informational note, not an enforceable limit, but a long feeder deserves the check).
  • The cottage is its own building: grounding and the disconnecting means at the building are settled with your electrician and the inspector.
  • Outdoor receptacles, entrance lighting and alarm placement follow the same rules as a house.

Planning an ADU in Circuia

Draw the ADU's rooms on the grid in feet and inches. Equip the rooms places the receptacles by the 210.52 rules (6 ft wall rule, 24 in countertop rule, 3 ft from the basin) and a switched lighting outlet in each room. Automatic wiring builds the branch circuits: 14 AWG / 15 A lighting, 12 AWG / 20 A receptacles, the two 20 A small-appliance circuits, the 20 A bathroom circuit, and 240 V two-pole circuits for the range and water heater. The check flags missing GFCI / AFCI protection and wire sizes that don't match breakers.

The PDF export on Letter paper gives you the floor plan with symbols, the ADU panel schedule, a single-line diagram and the materials list, useful for quotes and the permit application; a share link lets the owner or the designer follow along. Circuia does not decide between a feeder and a separate service and does not compute the load calculation: those stay with your electrician and the permit office. Drawing and checking are free; the Project Pass ($45 one-off, plus sales tax) unlocks the exports for one project.

Draw your ADU in the editor, free, in your browser.

Common mistakes

  • Assuming a separate meter is allowed (or required) without asking the utility and the permit office.
  • Bonding neutral and ground in the ADU subpanel: the bond belongs only at the service.
  • Adding an all-electric ADU to an existing service without a load calculation.
  • Keeping the old garage receptacle circuit in a converted garage instead of wiring it as habitable rooms.
  • Forgetting smoke and CO alarms because the ADU is "just a studio".

Frequently asked questions

Does an ADU need its own electrical service?

Not necessarily. Many ADUs are fed from the main house panel through a feeder to a subpanel; others get a separate service and meter from the utility. Which option is allowed or required depends on your jurisdiction and your utility, and the choice also depends on whether the existing service can carry the added load. Ask the permit office and the utility before you design.

How is an ADU subpanel grounded?

When the ADU is fed by a feeder from the main house, the subpanel gets a 4-wire feeder (two hots, neutral, equipment ground). The neutral bar is isolated from the enclosure and the grounds land on a separate bar, because the neutral-to-ground bond exists only at the service disconnect (NEC 250.24(A)(5), 250.142(B)). A detached building adds local grounding questions for your electrician and inspector.

Do I need a load calculation to add an ADU?

Usually yes when the ADU is fed from the existing service: the permit office wants to know the service can carry the added load. The NEC has a method for existing dwellings (220.83; Article 120 in NEC 2026). An electric range, water heater and heat pump in the ADU weigh the most and can push a 100 A house toward a service upgrade.

What circuits does a small ADU need inside?

The same as any dwelling: two 20 A small-appliance circuits for the kitchen countertops, a 20 A bathroom circuit, general lighting and receptacle circuits, a laundry circuit if there is laundry, and 240 V circuits for the range, water heater and heat pump. GFCI and AFCI apply by room, and smoke alarms are hard-wired and interconnected, with CO alarms where required.

Can Circuia plan an ADU?

It plans the inside of the unit: receptacles placed by the NEC 210.52 rules, switched lighting, branch circuits, GFCI / AFCI and wire-size checks, then a floor plan, panel schedule, single-line diagram and materials list on Letter paper. The supply choice and the load calculation stay with your electrician and the permit office. The US rules pack does not replace a licensed electrician.

Design aid

Design the installation with this country's rules

Draw the home or describe it to the AI: Circuia places the points, checks the country's rules in real time and generates the consumer unit, single-line diagram and bill of materials.

Open a free sample plan with these rules

Written by

Circuia team

Written by the Circuia team from the sources listed and from the editor's rules pack for this country: the values in the tables are the ones Circuia uses.

Published · updated