An accessory dwelling unit (ADU), whether a converted garage or a new backyard cottage, raises two electrical questions. Outside: how it is supplied, by a feeder from the house panel to a subpanel or by its own utility service, and whether the existing service can carry the added load. Inside: a small home with its own kitchen, bathroom and bedroom, wired to the same NEC dwelling rules as the main house. Both depend heavily on your jurisdiction.
Updated on Last checked NEC (NFPA 70) 2023
Key facts
- 01How an ADU is supplied (feeder and subpanel from the main house, or a separate service and meter) depends on the jurisdiction and the utility, not on a single NEC rule.
- 02A subpanel keeps neutral and ground separate (isolated neutral bar, 4-wire feeder): the neutral-to-ground bond exists only at the service (250.24(A)(5), 250.142(B)).
- 03Adding an ADU to an existing service usually needs a load calculation for the added load (220.83 for existing dwellings, Article 120 in NEC 2026).
- 04Inside, the usual dwelling rules apply: 2 × 20 A small-appliance circuits if there is a kitchen, a 20 A bathroom circuit, GFCI / AFCI, the 6 ft wall rule, smoke alarms.
- 05A garage that becomes living space is wired as habitable rooms: receptacle spacing, AFCI, switched lighting, alarms.
ADU rules start at the permit office
The NEC does not have an "ADU article". What decides the electrical design is how the jurisdiction classifies the unit, what the utility allows for metering, and the general dwelling rules of the NEC and the IRC. Ask the permit office early: whether a separate meter is allowed or required, whether the ADU may be fed from the main house panel, and which load calculation they want to see.
Feeder from the house or separate service?
| Option | What it means | Points to check |
|---|---|---|
| Feeder from the main panel | A two-pole breaker in the house panel feeds a subpanel in the ADU through a 4-wire feeder (two hots, neutral, equipment ground) | Room in the main panel; capacity of the existing service (load calculation); neutral and ground kept separate in the subpanel |
| Separate service | The utility installs a second meter (or the ADU gets its own service drop or lateral); the ADU panel is a service panel | Utility rules and fees; whether the jurisdiction allows a second service on the lot; outdoor emergency disconnect (230.85) and surge protection (230.67) at that service |
With a feeder and subpanel, the key grounding rule is that the neutral is bonded to ground only at the service disconnect of the main house (250.24(A)(5), 250.142(B)). In the ADU subpanel, the neutral bar is isolated from the enclosure and the equipment grounding conductors land on a separate ground bar. A detached cottage raises further grounding and feeder-routing questions that your electrician and inspector will settle locally.
Remember that the ADU subpanel or service panel is a panel like any other: 30 in wide, 36 in deep, 6.5 ft high working space (110.26), never in a bathroom or a clothes closet (240.24), and a complete circuit directory (408.4).
Can the existing service carry the ADU?
When the ADU is fed from the house, the permit office will usually want to see that the existing service can carry the added load. For an existing dwelling, the NEC has a dedicated method for added loads (220.83; relocated to Article 120 in NEC 2026). Like the optional method for one-family dwellings (220.82), it starts from 3 VA per ft² of floor area, 1,500 VA per small-appliance and laundry circuit and the nameplates of fastened-in-place appliances, applies demand percentages, then adds heating and cooling. Your electrician applies the exact percentages of the edition your jurisdiction uses.
What weighs most in an ADU: an electric range or cooktop, a water heater, a heat pump or mini-split, and a dryer if there is one. An all-electric ADU on a 100 A house service often brings the question of a service upgrade; a gas-heated main house on 200 A may have room. The calculation decides, not the rule of thumb. See residential load calculation (NEC 220).
Inside the ADU: the same dwelling rules as the main house
| Space | Receptacles and lighting | Circuits and protection |
|---|---|---|
| Living / sleeping area | No point along a wall more than 6 ft from a receptacle; wall-switched lighting outlet (or switched receptacle) | AFCI; general 15 / 20 A circuits |
| Kitchen or kitchenette | Countertop receptacles: no point more than 24 in away; island provision for a future receptacle | 2 × 20 A small-appliance circuits; GFCI on all receptacles + AFCI |
| Bathroom | Receptacle within 3 ft of the basin; switched light; exhaust fan | 20 A bathroom circuit; GFCI |
| Laundry (if any) | Receptacle for the washer | 20 A laundry circuit; GFCI + AFCI; 30 A 240 V dryer circuit |
| Outside | Receptacle at the entrance and switched entrance light | GFCI; weather-resistant receptacle with in-use cover |
| Alarms | Smoke alarm in the bedroom (or sleeping area), outside it and on each story; CO alarm with fuel-burning appliances or an attached garage | Hard-wired, battery backup, interconnected |
Typical 240 V circuits in an ADU: a range at 40 A / 8 AWG (a two-burner cooktop or a compact range may be smaller, per its nameplate), a water heater at 30 A / 10 AWG for a 4,500 W element, and the heat pump or mini-split per its nameplate MCA and MOCP. Always size from the nameplates of the appliances actually chosen.
Garage conversion: what changes
- A garage has its own NEC rules (a 20 A garage circuit, one receptacle per vehicle bay, GFCI). Once it becomes living space, the habitable-room rules apply instead: the 6 ft wall rule, AFCI, a wall-switched light in each room.
- If the main panel is in the garage, it now sits in the ADU: keep its working space clear and make sure it does not end up in the new bathroom or a closet.
- Draw the new rooms as they will be used (bedroom, kitchen, bathroom) and plan the circuits from that layout, rather than starting from the garage's existing receptacle circuit.
Backyard cottage: what changes
- The feeder or the separate service has to reach the cottage: trench length, route and wire size are part of the design (voltage drop of 3 % on a branch and 5 % total is an informational note, not an enforceable limit, but a long feeder deserves the check).
- The cottage is its own building: grounding and the disconnecting means at the building are settled with your electrician and the inspector.
- Outdoor receptacles, entrance lighting and alarm placement follow the same rules as a house.
Planning an ADU in Circuia
Draw the ADU's rooms on the grid in feet and inches. Equip the rooms places the receptacles by the 210.52 rules (6 ft wall rule, 24 in countertop rule, 3 ft from the basin) and a switched lighting outlet in each room. Automatic wiring builds the branch circuits: 14 AWG / 15 A lighting, 12 AWG / 20 A receptacles, the two 20 A small-appliance circuits, the 20 A bathroom circuit, and 240 V two-pole circuits for the range and water heater. The check flags missing GFCI / AFCI protection and wire sizes that don't match breakers.
The PDF export on Letter paper gives you the floor plan with symbols, the ADU panel schedule, a single-line diagram and the materials list, useful for quotes and the permit application; a share link lets the owner or the designer follow along. Circuia does not decide between a feeder and a separate service and does not compute the load calculation: those stay with your electrician and the permit office. Drawing and checking are free; the Project Pass ($45 one-off, plus sales tax) unlocks the exports for one project.
Draw your ADU in the editor, free, in your browser.
Common mistakes
- Assuming a separate meter is allowed (or required) without asking the utility and the permit office.
- Bonding neutral and ground in the ADU subpanel: the bond belongs only at the service.
- Adding an all-electric ADU to an existing service without a load calculation.
- Keeping the old garage receptacle circuit in a converted garage instead of wiring it as habitable rooms.
- Forgetting smoke and CO alarms because the ADU is "just a studio".
Frequently asked questions
Does an ADU need its own electrical service?
How is an ADU subpanel grounded?
Do I need a load calculation to add an ADU?
What circuits does a small ADU need inside?
Can Circuia plan an ADU?
Design aid
Design the installation with this country's rules
Draw the home or describe it to the AI: Circuia places the points, checks the country's rules in real time and generates the consumer unit, single-line diagram and bill of materials.
Written by
Circuia team
Written by the Circuia team from the sources listed and from the editor's rules pack for this country: the values in the tables are the ones Circuia uses.
Published · updated
Sources
Sources used for this page, official texts first:
- NFPA 70 National Electrical Code 2023 — free read-only access
- NFPA 70 National Electrical Code 2026 — free read-only access
- ICC — IRC R314 smoke alarms (PDF)
- City of Boise — IRC smoke and CO alarm handout
- EC&M — unpacking key revisions to the 2026 NEC (adoption status)
- Expertce — residential load calculation (NEC 220)
Related pages
- GuideNEC 2023 for homes: the residential rules that matter (National Electrical Code)NEC 2023 for one- and two-family homes: required circuits, receptacle spacing, GFCI/AFCI, wire sizes, panel and permits. Plus a free NEC compliance check.
- GuideResidential load calculation (NEC 220) explained, with a worked exampleNEC Article 220 load calculation for a house: 3 VA/ft², demand factors, range, dryer and EV loads, standard vs optional method, worked 2,000 ft² example.
- GuideHow to draw an electrical plan for a permit (US homes, NEC 2023)What US permit offices ask for on a residential electrical plan: receptacles, lights, smoke alarms, panel schedule, load calc and symbols, step by step.
- GuidePanel schedule template for a house (NEC 408.4 circuit directory)A panel schedule template for a house: the columns to fill, a filled 200 A example with L1/L2 positions, NEC 408.4 labeling rules and 110.26 working space.
- CircuiaPricing: free, Project Pass €29, Pro €49/monthCircuia plans: Free to explore, Project Pass at €29 incl. VAT for a homeowner project, Pro at €49 excl. VAT/month and Team at €129 excl. VAT/month for electricians. 14-day trial.