Canadian Electrical Code for houses: the CE Code 2024 rules that matter (and Québec)

The Canadian Electrical Code, Part I (CE Code, CSA C22.1) sets the wiring rules for Canadian homes, adopted province by province. Most provinces are on the 2024 edition; Québec applies its own chapter V, based on the 2021 edition. This guide covers what matters for a house: 120/240 V branch circuits, where receptacles go, GFCI and AFCI, the panel, and who may do the work.

Updated on Last checked CSA C22.1:24 (CE Code) · beta

Key facts

  • 01Most provinces and territories apply the CE Code 2024 (26th edition), Ontario through the OESC. Québec applies the Code de construction, chapter V, based on the 2021 edition with Québec amendments, in force since 26 March 2026.
  • 02Homes are fed 120/240 V single-phase, 60 Hz: 120 V circuits on L1 or L2; range, dryer, water heater, baseboards and EV charger at 240 V on a 2-pole breaker.
  • 03Copper wire and breaker: 14 AWG → 15 A, 12 AWG → 20 A, 10 AWG → 30 A, 8 AWG → 40 A; at most 12 outlets on a 15 A circuit (Rule 8-304).
  • 04Receptacles: no point along a usable wall more than 1.8 m from one; at least 2 kitchen counter circuits (15 A split or 20 A T-slot receptacles).
  • 05Class A GFCI near sinks, tubs, showers and outdoors; combination AFCI on receptacle circuits, except the counter, fridge and bathroom-only circuits.
  • 06Permits differ by province: ESA notification in Ontario, Technical Safety BC permits, municipal permits elsewhere. In Québec, only a licensed master electrician may do the work.

Which CE Code edition applies in your province?

CSA Group publishes the Canadian Electrical Code, Part I every three years. It only applies once a province or territory adopts it, usually with amendments: Ontario's version is the Ontario Electrical Safety Code, British Columbia's the BC Electrical Code, Québec's the chapter V – Électricité of its Construction Code. For a house, the edition that counts is the one in force on the date of the permit or notification.

CE Code editions for dwellings (status reported by public sources, November 2026)
Province or territoryCodeEdition
OntarioOntario Electrical Safety Code (OESC)29th ed., based on CEC 2024 (since 1 May 2025)
British ColumbiaBC Electrical CodeCEC 2024 with BC amendments
Alberta, Saskatchewan, ManitobaCE Code with provincial amendmentsCEC 2024
Atlantic provinces, Yukon, NWTCE Code with amendmentsCEC 2024
NunavutCE Code2018 edition
QuébecCode de construction, chapitre V – ÉlectricitéCEC 2021 with Québec amendments
Sources: Québec.ca, RBQ, ESA, Technical Safety BC, Electro-Federation Canada adoption table. Confirm the edition with your provincial authority.

In Québec, the new chapter V has been in force since 26 March 2026. The old chapter, based on the 2015 CE Code, may still be used for work started before October 17, 2027, but the RBQ recommends designing to the new one. Watch the rule numbers: Section 26 was renumbered in 2018 and again in 2021, so older guides quote other numbers.

Supply voltage, service size and the panel

A Canadian house is supplied at 120/240 V single-phase, three-wire: two line conductors (L1 and L2) and a neutral. Receptacles and lights run at 120 V between one line and the neutral; large appliances run at 240 V between the two lines on a 2-pole breaker. The panel spreads the 120 V circuits over L1 and L2 to balance the load.

The minimum service is calculated with Rule 8-200: living area, space heating, range, water heater and, since 2024, EV charging (with simplified rules and energy management systems). In practice a new house gets a 100 A or 200 A service; in Québec, where electric baseboard heating dominates, 200 A is common and the connection follows Hydro-Québec standard E.21-10.

  • Leave spare spaces in the panel for future circuits (Rule 8-108); Québec adds two spaces for a 2-pole EV breaker while the EV infrastructure is not completed.
  • Label every circuit in the panel directory on the door.
  • Grounding and bonding follow Section 10; neutral and ground are bonded at the service only.

Wire sizes, breakers and outlets per circuit

Largest breaker for NMD90 copper wire (values used by Circuia)
WireLargest breakerTypical use
14 AWG15 AReceptacles, lighting
12 AWG20 AT-slot counter receptacles, bathroom
10 AWG30 ADryer, water heater, baseboards
8 AWG40 ARange, EV charger
6 AWG50 ALarge appliances
Rule 14-104 with Tables 2 and 4 (copper at 60 °C). The 50 A value for 6 AWG is a conservative figure still to be checked.

Rule 8-304 limits a 15 A circuit to 12 outlets and a 20 A circuit to 16. Lighting outlets count just like duplex receptacles. Circuia's auto-wiring stays a little below the limit to keep a margin.

Where receptacles go, room by room

The CE Code mostly sets where receptacles go rather than a count per room. In finished rooms, no point along the floor line of a usable wall (900 mm or wider) may be more than 1.8 m from a receptacle. Doorways, fireplaces and floor-level windows break the wall line.

Receptacles required in a dwelling (CE Code Rules 26-720 to 26-724)
RoomRequirementProtection
Living room, bedrooms, dining room1.8 m rule along usable wallsAFCI
Kitchen counterNo point of the counter more than 900 mm from a receptacle; islands and peninsulas; at least 2 circuitsGFCI within 1.5 m of the sink; no AFCI on counter circuits
BathroomA receptacle within 1 m of the basin, at least 1 m from the tub or showerClass A GFCI
Laundry roomWasher receptacle plus one more; dedicated circuitGFCI near the laundry sink
Attached garageOne receptacle per car spaceAFCI as applicable
OutdoorsAt least two receptacles (Québec: at ground-floor level)GFCI within 2.5 m of grade
2021 / 2024 numbering. Some subrule letters are still to be confirmed in the code text.

Counter receptacles are either 15 A split receptacles (each half on its own circuit, 14/3 cable on a handle-tied 2-pole 15 A breaker) or 20 A T-slot receptacles on 12 AWG. Every receptacle in a dwelling is tamper-resistant, and outdoor receptacles get a weatherproof in-use cover.

GFCI and AFCI: where are they required?

A Class A GFCI protects people from shock. It is required for receptacles within 1.5 m of a sink, tub or shower, and for outdoor receptacles within 2.5 m of grade (Rule 26-704). It can be a breaker in the panel or the first receptacle of the circuit.

A combination AFCI protects against fire. It covers 125 V receptacle circuits rated 20 A or less in a dwelling unit (Rule 26-658), except kitchen counter, fridge and bathroom-only circuits. A dual-function breaker provides both GFCI and AFCI.

Range, water heater, baseboards and EV charger

  • Range: 40 A circuit on 8 AWG, 14-50R receptacle, 240 V 2-pole breaker.
  • Water heater: 30 A on 10 AWG for a 4,500 W tank, continuous load.
  • Dryer: 30 A on 10 AWG, 14-30R receptacle.
  • Electric baseboards: 240 V, loaded to 80 % of the breaker at most; heating circuits of 30 A at most in a dwelling (Rule 62-114).
  • EV charger: dedicated circuit sized at 125 % of the charger current unless an EV energy management system is used (Rule 86-300); Circuia proposes 40 A on 8 AWG.

In Québec, every new single dwelling with a garage, carport or parking area needs basic EV infrastructure from the panel to an outlet box near the parking spot (chapter V, Rule 86-202), counted in the service calculation whether or not a charger is installed. The old chapter called for a 40 A, 240 V provision; the 2026 value is still to be confirmed.

Permits and who may do the work, by province

Paperwork for residential electrical work (summary)
ProvincePaperworkWho may do the work
OntarioNotification of work to the ESA, inspectionLicensed electrical contractor, or a homeowner in their own home
British ColumbiaPermit from Technical Safety BC or the cityLicensed contractor, or the owner of an owner-occupied single-family home
Other provincesMunicipal or provincial permit, inspectionVaries; homeowner permits are common
QuébecDéclaration de travaux to the RBQ by the contractor; connection request to Hydro-Québec for a new or modified serviceMaster electrician only (RBQ licence subclass 16, member of the CMEQ)
In Québec the RBQ inspects by sampling. Exemption thresholds for the declaration are to be checked with the RBQ.

Wherever you are, the work needs a permit or notification and an inspection before the walls are closed. A homeowner who may not do the work can still prepare a clear plan, decide where receptacles and lights go, and ask several electricians for quotes on the same basis.

Smoke and carbon monoxide alarms

Alarms come from the building code (National Building Code 9.10.19 and the provincial codes). In a new house they are hard-wired and interconnected with battery backup: one in every bedroom, one on every storey including the basement, and one in the hallway near the bedrooms. A carbon monoxide alarm is required with a fuel-burning appliance or an attached garage.

Electrical plan software with a CE Code check

Choose Canada when you create a project in Circuia, then the province (Québec switches to the chapter V variant). Auto-wire builds the 120 V circuits on L1 and L2, puts the counter receptacles on 2 circuits of 20 A, gives 240 V loads a 2-pole breaker and sets the GFCI and AFCI badges. The check flags undersized wire, too many outlets on a circuit and missing protection.

The PDF comes out on Letter paper with the plan, the panel, the single-line diagram and the materials list (NMD90 cable, 5-15R and 14-50R receptacles). See electrical plan software for Canada or draw your plan to the CE Code.

Common mistakes

  • Following a guide written for an older edition: Section 26 was renumbered twice and the AFCI scope changed.
  • Putting the whole kitchen counter on one circuit, or counter receptacles on an AFCI circuit shared with the living room.
  • Using 14 AWG wire on a 20 A breaker.
  • Forgetting GFCI on outdoor receptacles or near the laundry sink.
  • In Québec, starting work without a master electrician and a déclaration de travaux.
  • Building a new house in Québec without the EV infrastructure for the parking spot.

Frequently asked questions

Which edition of the Canadian Electrical Code applies to my house?

The edition your province or territory adopted, with its amendments, on the date of your permit or notification. Most provinces apply the 2024 edition (Ontario through the OESC 29th edition). Québec applies chapter V of its Construction Code, based on the 2021 edition with Québec amendments and in force since 26 March 2026. Nunavut is still on 2018.

Can a homeowner do their own electrical work in Canada?

In many provinces, yes, in their own owner-occupied home with a permit or notification and an inspection: Ontario through an ESA notification, British Columbia through a homeowner permit. Québec is the exception: only a master electrician holding an RBQ licence and member of the CMEQ may do the work. Check with your provincial authority before starting.

How many receptacles does a room need under the CE Code?

The CE Code does not set a count per room; it sets a spacing. No point along the floor line of a usable wall may be more than 1.8 m from a receptacle, and no point of the kitchen counter more than 900 mm. The bathroom needs one within 1 m of the basin, and the outside of the house at least two.

Where is GFCI protection required in a Canadian house?

For receptacles within 1.5 m of a sink, tub or shower (kitchen, bathroom, laundry room) and for outdoor receptacles within 2.5 m of grade. The GFCI must be Class A. It can be a breaker in the panel or the first receptacle of the circuit, which then protects the receptacles downstream.

What size service does a new house need?

The minimum comes from Rule 8-200, based on the living area and the loads (heating, range, water heater, EV charging). In practice 100 A or 200 A; 200 A is common in Québec with electric heat. The connection follows the utility's requirements, for example Hydro-Québec standard E.21-10.

Does Circuia replace an electrician or the inspection?

No. Circuia's Canada pack and its Québec variant are built from public sources and are in beta. They help you draw a residential electrical plan, check it against the CE Code and prepare a quote, but the work, the permit and the inspection stay with the licensed electrician and your provincial authority.

Design aid

Design the installation with this country's rules

Draw the home or describe it to the AI: Circuia places the points, checks the country's rules in real time and generates the consumer unit, single-line diagram and bill of materials.