NEK 400:2026 explained: Norway's wiring rules for homes, IT network included
NEK 400 is the Norwegian wiring standard, and NEK 400:2026 applies to all design and installation work from 1 July 2026. For a home it requires a 30 mA RCD on every final circuit, a stove guard (komfyrvakt), surge protection, minimum socket numbers per room and 30 % spare space in the consumer unit. Many homes still run on a 230 V IT network without neutral.
Updated on Last checked NEK 400:2026 · beta
Key facts
- 01NEK 400:2026 applies from 1 July 2026; the 2022 edition may still be used for design until 31 December 2026, with the work completed before the end of 2027.
- 02Every final circuit in a dwelling has its own 30 mA RCD (NEK 400-8-823, since 2010), in practice one RCBO (jordfeilautomat) per circuit.
- 03A stove guard (komfyrvakt) to EN 50615 has been mandatory since 1 July 2010 in every new installation and whenever a new cooker circuit is installed.
- 04Living rooms and bedrooms need 2 socket outlets per started 4 m²; the consumer unit keeps 30 % spare space.
- 05Since 2026, PVC-insulated cables are no longer allowed: the minimum fire-reaction class is Dca-s2,d2,a1.
What is NEK 400 and how does it relate to Norwegian law?
NEK 400, “Elektriske lavspenningsinstallasjoner”, is published by Norsk Elektroteknisk Komite (NEK). It is the Norwegian version of the international HD 60364 series plus national parts. The best known for homes is NEK 400-8-823, nicknamed the housing standard (bolignormen), which adds requirements that do not exist in most other countries.
The legal basis is the Regulation on low-voltage electrical installations (forskrift om elektriske lavspenningsanlegg, FEL, FOR-1998-11-06-1060). FEL sets the safety requirements; its § 10 and the guidance from the Directorate for Civil Protection (DSB) name the latest edition of NEK 400 as the preferred way to meet them. FEL also contains Norwegian national adaptations, for example the rule that no neutral conductor is used in an IT system.
| Edition | Applies from | Transition |
|---|---|---|
| NEK 400:2026 | 1 July 2026 | Current edition for all design and installation |
| NEK 400:2022 | 1 July 2022 | Design allowed until 31 December 2026, completion before the end of 2027 |
| NEK 400:2018 | 1 July 2018 | Replaced (allowed until the end of 2022) |
Main changes in 2026 relevant to homes, according to NHO Elektro and the trade press: PVC-insulated cables are banned, surge protective devices on IT and TT systems must be “fail-safe”, the kitchen socket rule changed, USB sockets (where fitted) must be USB-C, a data outlet no longer needs a power socket next to it, an existing circuit may no longer be reused to charge an EV in a detached garage, and bonding of plastic drains in bathrooms was removed.
The Norwegian IT network, explained simply
Most of Europe distributes power as TN: three phases plus a neutral, 400 V between phases and 230 V between a phase and the neutral. A large part of Norway instead uses an IT network at 230 V between phases, with no neutral conductor (IT-nett). Sources estimate that roughly 70 to 80 % of buildings are still supplied this way, although that figure dates from older surveys; new areas have mostly been built with TN 400/230 V since the 1990s, and NEK 350 (2025) guides conversions from IT to TN.
- On IT, a normal 230 V appliance is connected between two lines (L1-L2, L2-L3 or L3-L1), not between a line and a neutral. There is no 400 V.
- Because both conductors are live, protective devices must switch both lines: circuits use 2-pole breakers and RCBOs. A 1-pole-plus-neutral RCBO designed for TN is not suitable on IT.
- A 230 V circuit on IT uses a cable with two conductors plus protective earth (3G); a three-line circuit uses 4G.
- A first earth fault on IT does not trip anything by itself. In a home, safety relies on the 30 mA RCD on every final circuit required by NEK 400-8-823.
- An EV charger on IT is usually single-phase between two lines, up to about 7.4 kW (32 A). Three-phase charging on 3 × 230 V is supported by very few cars.
| Supply | Voltage | Neutral | Circuit poles (230 V load) | Example capacity |
|---|---|---|---|---|
| IT (“2×” or “3×” connection) | 230 V between lines | No | 2-pole, both lines switched | 2 × 20 A ≈ 4.5 kW … 2 × 50 A ≈ 11.5 kW |
| TN-C-S (“4×” connection) | 400 V between phases, 230 V phase-neutral | Yes | 1-pole + neutral | 4 × 20 A ≈ 14 kW … 4 × 80 A ≈ 55 kW |
| TT | Up to 230 V | — | Protection by RCD only | — |
Circuits, breakers and the I2 ≤ Iz rule
Norway applies a stricter coordination rule to dwellings: for cables up to 4 mm², the conventional tripping current of the breaker (I2) must not exceed the current-carrying capacity of the cable (Iz), reported as clause 823.433.1. The general HD 60364 rule allows I2 up to 1.45 Iz. In an insulated wall (installation method A1), 2.5 mm² copper carries 19.5 A, so a 16 A breaker only complies if its I2 is about 1.2 × In (19.2 A), as modern RCBOs claim.
| Copper section | Iz, method A1 | Largest breaker | Typical use |
|---|---|---|---|
| 1.5 mm² | 14.5 A | 10 A | Lighting |
| 2.5 mm² | 19.5 A | 16 A | Socket circuits, washing machine, water heater (varmtvannsbereder) |
| 4 mm² | 26 A | 20 A | Heating, larger loads |
| 6 mm² | 34 A | 32 A | Cooker on IT (usual 25 A 2-pole) |
- NEK 400 sets no maximum number of sockets per circuit in the public sources we found; Circuia plans about eight per circuit as practice.
- A cooker or induction hob on IT is usually a 25 A 2-pole circuit (practice, to be confirmed); on TN it is often three-phase.
- Direct electric heating (panel heaters, underfloor heating cables) is very common. Each underfloor heating system (varmekabel) needs 30 mA protection and a documentation sheet.
- Whether washing machines, dryers, dishwashers and water heaters must have dedicated circuits is not stated in public sources; dedicated circuits are usual practice.
RCD per circuit, surge protection and the stove guard (komfyrvakt)
| Device | Rule | Since / source |
|---|---|---|
| 30 mA RCD (jordfeilbryter) | One per final circuit, usually an RCBO (jordfeilautomat), 2-pole on IT | 2010, NEK 400-8-823.411.3.3 |
| RCD type | Type A by default; EV charging type B or type A with 6 mA DC detection (RDC-DD) | NHO Elektro; type AC status not confirmed |
| Surge protection (overspenningsvern) | Mandatory in every low-voltage installation; type 2 in homes, fail-safe on IT and TT since 2026 | 1 July 2010, NEK 400 443 / 823 |
| Stove guard (komfyrvakt) | Mandatory for new installations and every new cooker circuit, including holiday homes; EN 50615 | 1 July 2010, elsikkerhetsportalen |
| Owner's RCD test | Press the test button at least once a year | elsikkerhetsportalen |
The stove guard (komfyrvakt) is a small device that monitors the hob and cuts its supply if it detects overheating or an unattended pan. It is one of the most searched Norwegian requirements because it applies not only to new homes but every time a new circuit is run to the cooker. A sub-board more than 10 m from the main board normally gets its own type 2 SPD, and an SPD in an outdoor cabinet must warn the owner when it fails.
Minimum sockets per room (bolignormen)
Unlike most European standards, NEK 400-8-823 sets minimum numbers of socket outlets (uttak) per room. One outlet is one socket, so a double socket counts as two.
| Room | Minimum |
|---|---|
| Living room, bedroom, study, family room (stue, soverom, arbeidsrom, allrom) | 2 per started 4 m² |
| Kitchen worktop (2026, islands included) | 2 for the first 2 m, then 1 per additional started metre (our reading of the 2026 rule) |
| Kitchen, fixed appliances | 1 per fixed appliance |
| Kitchen dining area | At least 4 |
| Entrance and hall (gang, entré) | 2 per started 6 m² |
| Bathroom (bad) | 2 (1 if the bathroom is under 3 m²), plus one per fixed appliance |
| Storage room, laundry (bod, vaskerom) | 2 |
| Each balcony or terrace | At least 2 |
| Media location | 6 |
| Consumer unit (sikringsskap) | 30 % spare space |
Bathrooms (våtrom) and underfloor heating
| Zone | Extent | Minimum IP rating |
|---|---|---|
| 0 | Inside the bath or shower tray | IPX7 |
| 1 | Above the bath or shower up to 2.25 m | IPX4 |
| 2 | 0.6 m beyond zone 1 | IPX4 |
| Sockets | Only outside zone 2 | — |
Underfloor heating cables (varmekabler) must be double-insulated or screened, with the metal mesh or screen earthed, 30 mA protection on each heating circuit, and a documentation sheet for each system. The thermostat of a heating cable stays outside zones 0 to 2.
EV charging (NEK 400-7-722)
- Every charging point has 30 mA protection, type B or type A with RDC-DD. Mode 3 with a Type 2 connector is recommended.
- The circuit is sized with a load factor of 1 (the charger may draw its full current for hours) unless load management is installed.
- Since 2026, an existing circuit may not be reused to charge a car in a detached garage.
- On IT, charging is usually limited to about 7.4 kW (32 A between two lines). On TN, three-phase 16 A gives 11 kW and 32 A gives 22 kW.
Who may do the work: the declaration of conformity (samsvarserklæring)
In Norway, electrical installation work is done by an electrical contractor registered in the Electrical Contractors Register (elvirksomhetsregisteret), with a qualified responsible person (faglig ansvarlig). There is no third-party inspection before the installation is used. Instead, the contractor tests the work and issues a declaration of conformity (samsvarserklæring), which has been required for all work since 1 January 1999.
| Document | Content |
|---|---|
| Samsvarserklæring (declaration of conformity) | States that the work complies, and which NEK 400 edition was applied |
| Risikovurdering (risk assessment) | Design assumptions, special conditions, justified deviations |
| Sluttkontroll (final inspection report) | Visual inspection, measurements and tests |
| Kursfortegnelse (circuit list) | What each circuit supplies, breaker ratings and cable sizes |
Planning a NEK 400 installation with Circuia
Choose Norway when you create the project, then the supply: IT 3 × 230 V (no neutral) or TN 400/230 V. On IT the editor gives every 230 V circuit a 2-pole RCBO and a line pair, balances the pairs, checks I2 ≤ Iz for cables up to 4 mm², adds the stove guard and a surge protective device, counts the bolignormen socket minimums room by room and keeps 30 % spare space in the consumer unit. The circuit list (kursfortegnelse), single-line diagram and bill of materials follow.
Open the editor set up for Norway (free, in your browser). Other Nordic countries: Sweden, Denmark, Finland, or the overview of all standards.
Common mistakes
- Using 1-pole + neutral RCBOs on an IT supply: both lines must be switched.
- Sharing one RCD between several final circuits in a dwelling.
- Forgetting the stove guard (komfyrvakt) when running a new cooker circuit.
- Protecting 2.5 mm² cable in an insulated wall with a 16 A breaker whose I2 exceeds 19.5 A.
- Counting a double socket as one outlet when checking the bolignormen minimums.
- Filling the consumer unit without leaving 30 % spare space.
- Ordering PVC-insulated cable for work under NEK 400:2026.
Frequently asked questions
What changed in NEK 400:2026?
What is the IT network in Norway?
Is a komfyrvakt (stove guard) mandatory?
How many sockets does a bedroom need under NEK 400?
Does every circuit need its own RCD in Norway?
Can I do my own electrical work in Norway?
Does Circuia certify an installation to NEK 400?
Design aid
Design the installation with this country's rules
Draw the home or describe it to the AI: Circuia places the points, checks the country's rules in real time and generates the consumer unit, single-line diagram and bill of materials.
Written by
Circuia team
Written by the Circuia team from the sources listed and from the editor's rules pack for this country: the values in the tables are the ones Circuia uses.
Published · updated
Sources
Sources used for this page, official texts first:
- Lovdata — FEL, Forskrift om elektriske lavspenningsanlegg (FOR-1998-11-06-1060)
- Lovdata — FEL national adaptations to NEK 400 (no neutral in IT)
- DSB — transition rules for NEK 400
- NHO Elektro — NEK 400:2026 er lansert
- Elsikkerhetsportalen — bolignormen (NEK 400-8-823)
- Elsikkerhetsportalen — komfyrvakt
- Elsikkerhetsportalen — samsvarserklæring
- DSB — registration in the Electrical Contractors Register
- NHO Elektro — EV charging (elbillading)
- Elvia — capacity per connection
- elektro247 — 8 viktige endringer i ny NEK 400
Related pages
- OverviewElectrical wiring standards in Europe, country by countryHome wiring rules explained for the UK (BS 7671), Ireland (I.S. 10101), Norway, Sweden, Denmark and Finland, with the Circuia editor for each country.
- GuideSS 436 40 00 explained: Sweden's wiring rules for homes (Elinstallationsreglerna)SS 436 40 00 edition 4 for Swedish homes: elsäkerhetslagen, authorised electricians, 30 mA RCDs, 10 A on 1.5 mm², three-phase supply and egenkontroll.
- GuideDanish wiring rules explained: DS/HD 60364 and the installation order BEK 1082Denmark's wiring rules for homes: BEK 1082 and DS/HD 60364, TT earthing, 30 mA type A RCDs, 13 A sockets, one socket per 4 m² and authorised electricians.
- GuideSFS 6000 explained: Finland's wiring rules for homes (SFS 6000:2022)SFS 6000:2022 for homes in Finland: Tukes and registered contractors, type A 30 mA RCDs, 10 A on 1.5 mm², 3 × 25 A supply and the commissioning inspection.
- CircuiaPricing: free, Project Pass €39, Pro €49/monthCircuia plans: Free to explore, Project Pass at €39 incl. VAT for a homeowner project, Pro at €49 excl. VAT/month and Team at €129 excl. VAT/month for electricians. 14-day trial.
- CircuiaCircuia: AI wiring plans to BS 7671 and EU standardsDraw your home or ask the AI: Circuia designs circuits and the consumer unit, checked against BS 7671, I.S. 10101 and the rules of 17 European countries.